COMMUNITY DEVELOPMENT DEPARTMENT
Administration
First Nandina
The First Nandina project was approved by the Planning Commission on October9, 2014. No appeal was filed
on the project. Demolition of the previously existing structures on the site was completed in April, 2016. The
project proposes to construct a 1.45 million square foot warehouse/distribution center on 73 acres located at
the southwest corner of Indian Street and Nandina Avenue in the Moreno Valley Industrial Area. The
developer, First Industrial Properties, has received strong early interest from potential tenants.
First San Michele Logistics
First Industrial is constructing a 187,000 square foot logistics facility at San Michele Road and Perris
Boulevard. The structure is nearing completion and the tenant, Wiseway Transportation Services, has been
issued a Temporary Certificate of Occupancy for storage purposes while construction is being
completed. Community Development, along with other departments, is working with the developer and
tenant to get the facility ready for use on a permanent basis as soon as possible.
March Business Center/Western Realco
Western Realco’s March Business Center project at the southeast corner of Iris Avenue and Heacock Street, in
the Moreno Valley South Industrial Area, is over 70% complete to date. The project was approved for 1,484,000
square feet of warehouse/logistics space on the 75-acre site. The first two buildings, the larger of which
encompasses 1,103,000 square feet, is complete. Western Realco has stated they have sold both buildings to
a buyer that has a potential tenant.
Karma Automotive
The tenant improvement for Karma Automotive, at 17100 Perris Boulevard, is approximately 98% complete.
To date, over 20 permits have been issued for various segments of work. The construction of the new office
area, which commenced mid-November, is now complete. The process of testing of all assembly and paint
equipment, robots, computers, and procedures is complete or near completion. Karma has been constructing
“test” vehicles over the summer and is gearing up for full production.
Building & Safety Division
Major Projects
Plans have been submitted for a 104 guest room Holiday Inn Express at the northeast corner of Day and
Eucalyptus, the former site of Robertson’s Ready Mix. This is the first plan check submittal for the “Quarter
Project” which will eventually consist of two hotels, a service station with convenience store and fast food
restaurant, a drive-thru fast-food restaurant, and two retail/restaurant buildings.